Tranquille Road Sanitary Main and Road Enhancement Project | Phase 3

Timeline
June 9, 2025–Fall 2026
Impacts
Detour in Effect
Expect delays
Lane closure
Road Closed - Local Traffic Only
Traffic Pattern Change
Transit
Location
Tranquille Road from Crestline Street to Southill Street

The City of Kamloops has contracted PME Construction to undertake Phase 3 of the Tranquille Sanitary Main and Road Enhancement Project between Crestline Street and Southill Street.

We are advising residents that work is scheduled to begin in early June 2025, with completion anticipated in fall 2026. The project will be split into 3 stages outlined in the map below:

  • Stage 1 – 2025: Crestline Street to Downie Street
  • Stage 2 – 2026: Downie Street to Windbreak Street
  • Stage 3 – 2026: Windbreak Street to Southhill Street

During the work, Tranquille Road will be open to local traffic only for driveway access, however, no thru traffic will be permitted.

IMPORTANT NOTE: The Dangerous Goods and Truck Route detour is: Ord Road to 8th Street. Drivers must travel along Ord Road instead of Tranquille Road during construction (early June until the end of 2025). If trucks travel down Tranquille Road past Airport Road, there will be no exit for them once they approach the construction zone at Tranquille Road and Crestline Street, and turning around with a large truck will be difficult.

Learn more about project sequencing, timelines, and traffic/transit impacts, visit LetsTalk.Kamloops.ca/TranquillePhase3.