Springhill Drive Improvements

Timeline: 
2020
Status: 
Current
Type: 
Roadway
Contact: 
BA Dawson Blacktop Ltd

Project Scope

The City of Kamloops has contracted BA Dawson Blacktop Ltd to carry out asphalt repairs and road improvements on Springhill Drive from Summit Drive to Sedona Drive. The project includes:

  • milling and paving
  • construction of bus pad
  • addition of accessible ramp to bus stop
  • minor utility repairs
  • pavement markings 

Traffic Impacts

Traffic may be single-lane alternating during portions of construction. Please obey all traffic control personnel and signage when driving in the vicinity of the project. 

Hours of Work

Work will begin September 8, with completion anticipated by the end of September. Construction is scheduled to occur Monday through Saturday, 7:00 am–5:00 pm. 

Residents, Pedestrian and Transit Access

Access for residents, businesses and pedestrians will be maintained throughout the project. Transit will be given priority access through the construction zone. Bus stops may be temporarily relocated.