Kamloops-Princeton Highway Project

Timeline: 
2018
Status: 
Past
Type: 
Roadway
Estimated cost: 
$600,000
Contact: 
Dawson Construction

Project Scope

The City of Kamloops has contracted Dawson Contruction Ltd to mill and pave the Kamloops-Princeton Highway (Hwy 5A) from City limits to just past the Long Lake Road intersection. They will also pulverize and pave approximately 500m of the Frontage Road across from Long Lake Road. 

Hours of Work 

Construction will take place from September 17 to mid-October, 2018. Working hours are 7:00 am to 7:00 pm, Monday to Saturday. 

Traffic Impacts

Traffic will be single lane alternating during the duration of the project. The Frontage Road will be limited to local traffic only, and a minimum of one entrance will be maintained at all times. 

Please obey all traffic control personnel and equipment and use caution when driving in the vicinity of the construction.

Resident Impacts

Residents are advised that throughout the construction period vibratory compaction equipment may be in use; therefore, any fragile items should be packaged or protected from damage due to vibration.  There may also be noise disruption due to equipment on site.