Fleetwood Avenue - Phase 1

Timeline: 
2021
Status: 
Current
Type: 
Roadway, Utilities
Contact: 
Internal
Updates: 
This project has been extended through November 2021.

Project Update - September 15

The City of Kamloops is extending the projected completion timeline of utility and road works and pedestrian upgrades on Fleetwood Avenue between Southill Street and Desmond Street. The expected completion is now the end of November 2021, due to the following unforeseen and extenuating circumstances:
•    staffing shortages;
•    heat stress impacts to outside workers;
•    wildfire smoke impacts to outside workers; and
•    unforeseen underground conflicts with other utilities.

Driveway Access Update

Driveway access to residents may be temporarily restricted during construction. With the addition of new curb, gutter, and sidewalk, once the concrete is poured, all properties will have their driveway access restricted for 7 days as the concrete will need time to cure. On-street parking restrictions are still in effect from 8:00 am to 4:00 pm Monday through Friday. Residents are asked to park on a neighbouring street during the time when their driveways are curing. 


Project Scope

The City of Kamloops will be conducting utility and road works as well as pedestrian upgrades on Fleetwood Avenue between Southill Street and Desmond Street. We are advising residents in the area that this work is scheduled to begin May 25 and will encompass the following scope of work:

  • water service replacements;
  • water main replacements; 
  • new drainage infrastructure;
  • sanitary upgrades;
  • pedestrian sidewalk; and
  • road reconstruction.

Resident Impacts

Throughout the construction period, vibratory compaction equipment may be in use; therefore, any fragile items should be packaged or protected from damage due to vibration. There may also be noise disruption due to equipment on site. 

In order to perform utility works, there will be frequent water interruptions. Expect intermittent water shutdowns of three hours or less during this portion of the project. When possible we will inform residents daily of longer duration water shutdowns in excess of three hours. We recommend that residents store a quantity of water for use during the longer duration periods.

Garbage collection will not be affected.

Hours of Work

Work will begin on May 25 and is expected to be complete in October. Construction is scheduled to occur Monday–Friday, 7:00 am–4:00 pm. Some evening or weekend work may be required.

Traffic Impacts

Fleetwood Avenue, between Southill Street and Desmond Avenue, will be closed for the duration of the project, with the exception of local traffic. 

Driveway access to residents may be temporarily restricted during construction. Residents are advised that off-street parking may not be accessible at times during construction and to plan ahead by moving vehicles to adjacent streets before work commences Monday to Friday. On-street parking is not permitted during working hours on weekdays.

Please obey all traffic control personnel and equipment when driving in the vicinity of the construction. 

Transit Route 2: Parkcrest will be detoured with regular traffic, with temporary stops as shown below. Visit bctransit.com/Kamloops for the most up to date impacts.