PROJECT SCOPE
The City of Kamloops will be extending water and sanitary mains in the 8200 area of Dallas Drive, between Peerless Way and Andover Crescent. We are advising residents and businesses in the area that this work is scheduled to begin mid-March depending on weather, and will encompass the following scope of work:
- extending water and sanitary mains;
- repaving of asphalt; and
- pavement markings.
TRAFFIC IMPACTS
Dallas Drive will be closed with the exception of local traffic. A detour route via Andover Cres/Peerless Way is provided. Please obey all traffic control personnel and equipment when driving in the vicinity of the construction.
BUSINESS AND TRANSIT IMPACTS
Business access will be maintained throughout the project.
Throughout the construction period, vibratory compaction equipment may be in use; therefore, any fragile items should be packaged or protected from damage due to vibration. There may also be noise disruption due to equipment on site.
Transit impacts are shown on the map below.
HOURS OF WORK
Work will begin mid-March, with completion anticipated for mid-May, 2021. Construction is scheduled to occur Monday–Friday, 8:00 am–4:00 pm, with the possibility of evening work.