Project Scope

The City of Kamloops has contracted Urban Appeal Landscaping Ltd. to carry out the installation of curb, gutter and sidewalk along the east side of 2nd Avenue from Lansdowne Street to the Sandman Hotel parking lot. 
 
The project includes:
 
  • installation of curb, gutter and sidewalk
  • asphalt replacement of lane adjacent to new curb
  • installation of paving stones
  • electrical upgrades

Traffic Impacts

Northbound lane closures will be in effect. There will be no access to the parking lot south of tracks via 2nd - detour route is via 3rd Avenue to the roundabout. Please obey all traffic control personnel and equipment when driving in the vicinity of the construction.

Hours of Work 

Construction will begin the week of September 4 and completion is anticipated for the end of September 2018. Construction is scheduled to occur Monday to Friday, from 7:00 am to 5:00 pm, with the possibility of some weekend work.

Business and Pedestrian Access

Pedestrian access will be maintained at all times on the west side of 2nd Avenue. Access to the Sandman Hotel will be also be maintained.