Share page


Lac Le Jeune Road Rehabilitation

Timeline
2022
Status
Upcoming
Type
Roadway
Estimated cost
$1.24 million
Contact
BA Dawson Blacktop

The City has contracted BA Dawson Blacktop Ltd. to perform drainage works and road upgrades to Lac Le Jeune Road. 

Starting Wednesday, March 23, crews will be roto-milling Lac Le Jeune Road between Sugarloaf Road and 1720 Lac Le Jeune Road. Hours of work will be 7:00 am to 5:30 pm. The roto-milling is expected to be complete on Saturday, March 26. 

This work is being carried out to temporarily improve the current road condition. The road will be left in a gravel state until paving occurs late May/early June.

Traffic will be single lane alternating during the roto-milling work. Please obey all traffic control personnel, signage and equipment when driving in the vicinity and expect some delays.