Average processing times for development applications.

Rezoning: 10 - 12 weeks
Official Community Plan Amendment: 10 - 12 weeks
Development Permit: 4 - 6 weeks
Development Variance Permit: 8 - 10 weeks
Board of Variance: Meets once a month, when they have a minimum of 3 applications
Preliminary Development Proposal Review: ~ 4 weeks
Sign Permit: 1 week
Liquor Licence Application: Please enquire
Change To An Existing Liquor Licence Permit: Please enquire
Temporary Commercial or Industrial Use Permits: 10 - 12 weeks
Business Licence: 1 day (home-based business) 15 - 18 days (commercial)
ALR applications: Please enquire
Subdivisions: Please enquire

Note: These timeframes only represent an average processing time. Depending upon the complexity of an application, volume of applications in receipt and staffing levels, these timeframes may be extended:

Contact
Planning and Development
105 Seymour Street
Kamloops, BC V2C 2C6
ph 250-828-3561
fax 250-828-3848
email planning@kamloops.ca

Note: All correspondence is entered into our system and will be directed accordingly. The City of Kamloops will endeavor to contact you within two business days. Thank you.