Notice

Development & Engineering Services

North Primary Sanitary Gravity Main Upgrade - Phase 1

Project Update - June 29, 2017

Tranquille Road
Crews are starting to work west of Aviation Way. Tranquille Road will be reduced to single-lane alternating traffic starting July 5, 2017 for the duration of the project.

Dangerous Goods and Truck Route Detour
From May 29 to September 1, this section of Tranquille Road will not be passable for large trucks. Ord Road has been designated as a temporary Dangerous Goods and Truck Route from 8th Street to Tranquille Road. Please expect increased truck traffic along this route.

Aviation Way
Aviation Way is open to all traffic.

Photo Gallery
Get a glimpse into what lies beneath the surface of our roads with our project photo gallery.

Project Details

The City of Kamloops has contracted with Extreme Excavating Ltd to carry out essential sanitary utility upgrades from the North Primary Lift Station on Aviation Way to Crestline Street.

The project consists of:

  • Sanitary main and storm main installation;
  • Multiple sanitary tie-ins including one at the North Primary Lift Station;
  • Water main crossings;
  • Concrete curb and gutter;
  • Full road reconstruction;¬†and
  • Pavement marking and signage.

 

Project construction began in February 2017, starting at the North Primary Lift Station on Aviation Way. Construction work started on Tranquille Road on May 26, 2017 and is expected to last approximately 8-12 weeks. Local residents and businesses will be given advance notice of when their driveway access will be disrupted. Where possible, accommodations will be made for alternate access to businesses during business hours.

The majority of the work will take place during the day from Monday to Friday, with the possibility of some weekend and night work. Anticipated hours of work will be 7:00 am - 7:00 pm.

Area of Work Area of Work Map

Please obey all traffic control personnel and equipment when in the vicinity of the construction. For traffic updates, please visit www.kamloops.ca/kammute or follow #kammute on Twitter.



Customer Service
Report an Issue

Contact
Public Works and Utilities
955 Concordia Way
Kamloops BC V2C 6V3
ph 250-828 3461
email publicworks@kamloops.ca

Note: All correspondence is entered into our system and will be directed accordingly. The City of Kamloops will endeavor to contact you within two business days. Thank you.