Heffley Creek Bridge Construction

Project Scope

The City has contracted Acres Enterprises Ltd. to construct a bridge to replace the existing multi-plate culvert that was damaged during the flooding this past spring. Work is scheduled to commence on October 23, 2017, with an anticipated completion by Spring 2018.

Work includes, but is not limited to:

  • removal and disposal of existing embankment and culvert
  • utility relocation and protection
  • construction of a new bridge structure
  • embankment and road restoration

Construction is scheduled to occur Monday-Friday, 7:00 am-5:00 pm, with additional night and weekend work being performed as required.

Residents are advised that throughout the construction period, vibratory compaction equipment will be in use; therefore, any fragile items should be packaged or protected from damage due to vibration.

The construction site will be closed to both vehicle and pedestrian traffic for the duration of the project. Please obey all traffic control personnel and equipment when driving in the vicinity of the construction.

» See Map/Diagram from our July 18, 2017 Open House
» Notice to Residents