Barnhartvale Road Full Depth Reclamation

Project Scope

The City of Kamloops has contracted BA Dawson Blacktop Ltd. to perform a full depth reclamation of Barnhartvale Road from Todd Road to Campbell Creek Road. The contractor is scheduled to commence work on September 6, 2017, with an anticipated completion by November 2017.

The project will consist of:

  • Rotomill and stabilize existing roadway
  • Supply and install asphalt pavement at 100mm thickness
  • Gravel shoulder restoration
  • Drainage ditching improvements

Construction is scheduled to occur Monday to Friday, 7:00 am-5:00 pm, with additional night/weekend work as required. Driveway access to residents may be temporarily restricted to accommodate construction; we regret any inconvenience this may cause. Advance notice will be provided whenever possible.

Residents are also advised that throughout the construction period, vibratory compaction equipment will be in use; therefore, any fragile items should be packaged or protected from damage due to vibration.

Residential garbage collection schedule will not be affected. To minimize any impact to residential garbage collection, please have your containers out by 7:00 am as per Solid Waste and Recyclables Bylaw No. 40-59.

Please obey all traffic control personnel and equipment when driving in the vicinity of the construction. For traffic information, visit Kamloops.ca/kammute or follow #kammute on Facebook and Twitter.