Notice

Development & Engineering Services

Update: February 23, 2017

The City of Kamloops is excited to announce that Westsyde Pool and Fitness Centre will be open to the public by late summer 2017.
Read more...

Update: January 10, 2017

Construction is currently paused after the discovery that incorrect building materials were delivered and partially installed by the general contractor.
Read more...

Westsyde Pool Construction Updates

Stories and Photos from the Westsyde Pool and Fitness Centre

As the Westsyde Pool and Fitness Centre continues to transform, we'll keep you in the loop with photos and short stories.

  • Big Beams and Big Dreams
  • » Check out our construction photos here



    Structural Repair Project

    The first step towards the re-opening of the Westsyde Pool took place in April 2016 as crews conducted geotechnical testing adjacent to the existing building foundation. This work was required to access ground conditions in order to complete the project design.

  • Elevation Drawing 1
  • Elevation Drawing 2
  • Elevation Drawing 3
  • The Centre remains closed to the public.



    Customer Service
    Report an Issue

    Contact
    Public Works and Utilities
    955 Concordia Way
    Kamloops BC V2C 6V3
    ph 250-828 3461
    email publicworks@kamloops.ca

    Note: All correspondence is entered into our system and will be directed accordingly. The City of Kamloops will endeavor to contact you within two business days. Thank you.